After the technical transmission-takeover the needed appendix had been collected and the request of the operation permission was also handed to the competent authority.

We have launched the authorization of the planned track.

The published article and film are seen on the following links:

film

article

 

 

With the date of 31th January 2016 the following works have been terminated:

-          the renewal of the Lake Bükki

-          the structural works of  the prohibited relief, related to the 3rd and 4th lakes of Kűvölgy and Lake Baláta, as well as the entrapment of the water streams.

 

The implementation passed off in order. The technical handover-takeover is going to take place on 16th February 2016.

 

Lake Bükk                                                                           Lake Kűvölgy

At the end of the implementation the completed works were being introduced to the forester and hunter collegaues.

 

 

The by-pass was constructed to regulate runoff from Lake Baláta.